Project profitability: data warehouse and BI, or FP&A?

A cost report shows how much the project has cost so far. The management board, however, asks something else: how much will we ultimately earn on it? See what a data warehouse and BI can deliver, and what an FP&A system adds.

How much has the project cost so far?

It is an important question. But from the perspective of the management board and the Project Manager, another one matters even more: how much will we ultimately earn on it?

We will not find the answer in accounting alone. We need data on the costs incurred, but also up-to-date knowledge about the remaining work, purchases, subcontractors, scope changes and risks. Only by comparing actuals with the budget and the current forecast do we get a realistic picture of project profitability.

This applies to construction, service and IT companies. Similar challenges are faced by project-based manufacturing companies which, within a single contract, design a solution, manufacture their own equipment or components, develop software, use subcontractors, and then install and commission everything at the customer’s site.

In such organisations an ordinary project cost report is definitely not enough.

#KEY TAKEAWAYS

A cost report shows what has already been posted. Project profitability only becomes visible when actuals are compared with the budget and the current forecast to completion.

  • Data warehouse and BI Integration and reporting of data that is already in the systems
  • FP&A system Budget, forecasts, versions and approvals in one model with actuals

Project budget and current forecast

The project budget is often created at the bidding stage. The company calculates revenue, materials, labour input, external services, transport, installation, commissioning and risks.

After the contract is signed, the calculation is refined and approved as the baseline budget. This is the reference point for later assessment of the project.

The budget alone, however, does not answer the question of what margin we expect today. During delivery, material costs, the scope of work, the schedule, subcontractor quotes, the team’s hours and delivery dates all change. There is also additional work, complaints and risks that could not be foreseen at the start.

That is why a regularly updated forecast for the whole project is needed. It should take into account costs and revenue recognised to date, commitments that have not yet been posted, and the remaining work and purchases. Current labour input, changes in the scope and value of the contract, risks and project contingencies, the delivery and invoicing schedule and the impact of exchange rates matter as well.

The budget shows the original assumptions. The forecast shows what we expect based on current knowledge.

How to monitor project delivery?

Reporting should show the project from several perspectives: the result for the current month, year-to-date and project-to-date actuals, the forecast to project completion and the expected result of the whole contract.

The project-to-date perspective is particularly important. Contracts often last longer than one financial year, and profitability has to be assessed for the whole undertaking, not only for the current period.

Two basic comparisons are also needed.

The first is the current forecast for the whole project versus the original budget. It shows how much of the assumed margin is left and which assumptions did not hold.

The second is the current forecast versus last month’s forecast. It shows what has changed since the last report. This lets the management board see at once on which projects the expected result is deteriorating and why.

A good profitability report should include, among other things:

  • the original and current contract value;
  • the baseline budget and approved changes;
  • monthly, annual and project-to-date actuals;
  • costs committed but not yet posted;
  • the forecast of revenue and costs to project completion;
  • the expected final cost;
  • the current margin in value and percentage terms;
  • the variance of the forecast from the original budget;
  • the change in the forecast compared with the previous month;
  • comments explaining the most important variances.

#TERMS

How to calculate the expected project margin?

  • Baseline budget BAC The approved budget for the whole project.
  • Estimate to complete ETC The forecast cost of the remaining work.
  • Estimate at completion EAC Costs incurred and committed plus the estimate to complete.
  • Expected margin The current contract value minus the estimate at completion.

Abbreviations follow the earned value methodology, described among others by the Project Management Institute.

What can a data warehouse and BI deliver?

A data warehouse and BI are good at integrating and reporting the data available in source systems.

They can combine information from ERP, accounting, time tracking, purchasing, inventory, CRM or project management systems. They then present it in the form of reports and dashboards.

In project controlling, a data warehouse and BI can provide automatic loading of actual data and a combination of financial and operational data. They make it possible to report project costs and revenue, analyse actuals against the loaded budget and prepare monthly and cumulative reports.

On top of that come analysis of the project portfolio, reporting by company, business unit, customer and Project Manager, and the ability to go from the project result down to the source document.

That is a lot. Still, we are mainly reporting data we already have.

If the budget and forecast are created in Excel, they can be loaded into the data warehouse and shown in Power BI. This does not solve the problem of collecting successive versions, verifying them, approving them and explaining the changes. Someone still has to collect the files from Project Managers, check that they are complete and prepare the data for reporting.

What does an FP&A system add?

An FP&A system handles budgeting, forecast updates and performance monitoring in a single data model.

Actual data is loaded automatically from source systems. Project Managers update forecasts and add information about remaining work, purchases, scope changes and risks. Controlling checks the completeness of the data, manages the process and analyses variances.

The same environment holds the original budget and successive forecast versions, actuals for the current month, cumulative actuals and project-to-date data, as well as the forecast of remaining revenue and costs and the expected margin of the whole contract.

The system can automatically prepare monthly, cumulative and project-to-date reports. It also shows the variance of the current forecast from the original budget and the change compared with the previous forecast.

As a result, you see not only the costs incurred. You also see how the expected project result is changing.

Beyond reporting itself, an FP&A system provides:

  • shared budget and forecast templates;
  • data versioning;
  • control of statuses and deadlines;
  • change history;
  • permissions for individual users;
  • approval of budgets and forecasts;
  • comments on variances;
  • currency translation;
  • consolidation of project results at the level of business units, companies and the whole group.
CriterionData warehouse and BIFP&A system
Actual data from ERP and other systemsLoaded automaticallyLoaded automatically
Project budget and forecastLoaded from finished filesCreated and updated in the system
Versions, deadlines and approvalsOutside the warehouse, usually in filesIn the system, with change history
Change in the forecast compared with the previous monthOnly if someone loads both versionsVersion comparison in the same model
Dashboards and visualisationsA strength of Power BIReports in Excel and data for Power BI

Is a data warehouse needed for project controlling?

Not always.

In many companies the number of active projects is somewhere between a dozen and several dozen. Over its whole lifetime, a single project may generate several hundred, sometimes several thousand documents. From a technology point of view, these are not particularly large data volumes.

The main challenge lies elsewhere. You need to assign data to projects correctly, connect actuals with the budget and forecast, and collect up-to-date knowledge from the people responsible for delivery.

An FP&A system can comfortably handle actual data and reporting of actuals as well. It also has an important advantage: the budget and forecast are already in it. There is no need to build separate mechanisms feeding the data warehouse with successive versions of the plan, or to reconcile structures between different solutions.

If the company already has a corporate data warehouse, it can remain the source of actual data for FP&A. Power BI, in turn, can be used for additional analyses and visualisations.

If, however, the main goal is to manage project budgets, update forecasts regularly and monitor the expected margin, an FP&A system can handle the whole process: from loading actuals, through the budget and forecast, to reports for Project Managers, controlling and the management board.

Project controlling in FlexiEPM

FlexiEPM combines actual data, budgets and forecasts in a single controlling model.

Data from finance and accounting systems, time tracking and other sources can be loaded automatically. Project Managers add the information that is not yet in accounting: the current plan of remaining work, expected purchases, scope changes, risks and the final forecast.

Controlling manages the structure of the process, versions, deadlines and permissions. The management board receives a consistent picture of the profitability of individual projects, business units, companies and the whole group.

It can also check how the forecast margin has changed over successive months and which projects are responsible for the change in the expected result.

FlexiEPM uses Excel as the user interface, while the data, rules and successive forecast versions are stored centrally. The system can also pass complete data covering actuals, budget and forecast to Power BI.

Author

  • Mariusz is co-founder and Managing Director of FlexiSolutions, with over 20 years of experience in controlling systems. He studied at Warsaw University of Technology and Kozminski University. Since 2023, he has led the ICV Regional Working Group in Warsaw and regularly shares his expertise at conferences and in industry publications.

    See all posts Mariusz Sumiński

Related Posts

Alternative to Oracle Hyperion and SAP BPC
Controlling

FlexiEPM as an alternative to Oracle Hyperion and SAP BPC – a comprehensive EPM system for controlling and consolidation

Many companies running Oracle Hyperion or SAP BPC are wondering what comes next: migration to Oracle Fusion Cloud EPM or another platform? FlexiEPM is a modern EPM system that combines budgeting, reporting and consolidation in one environment, fully integrated with Microsoft Excel and with support close to the user. See what your future after Hyperion could look like.

Read more >
ERP a EPM
Controlling

EPM vs ERP: does a company that has an ERP still need an EPM system?

The CFO of a mid-sized company usually has an ERP, Excel and one or two people in controlling. ERP shows well what has happened. Questions about the reasons and about what comes next end up in spreadsheets, and those are exactly the questions an EPM system answers. Whether you need both systems depends on your scale and on how your finance department works.

Read more >
excel w controllingu
Controlling

Is controlling doomed to Excel’s dominance? On the limits of using spreadsheets in controlling

Excel is a very good tool for data analysis. It works great for ad hoc analyses, model building and conceptual work, when one person wants to calculate something quickly and test different scenarios.

The problem begins when the spreadsheet becomes the foundation of the entire finance process. Excel was not designed for multi-user budgeting, the consolidation of a dozen or several dozen companies, work on large data volumes, or full control of versions and change history.

In a smaller company this works quite well. At a larger scale, the number of files, versions and manual operations grows, and with them the risk of errors and of losing control over the process.

Read more >

Book a Consultation with an expert

Streamline your planning, controlling, reporting, and consolidation processes in a single system.
Eliminate errors and reduce time-consuming tasks through integration and automation.
Mariusz Sumiński

Mariusz Sumiński

Managing Director, Co-Founder